BHEL Starts Kaleshwaram Lift Irrigation Scheme

BHEL has earlier commissioned 4 Units of the same project in April and May, 2019. Significantly, the pump for each unit is designed to lift 89.16 cumecs (cubic metres per second) of water by 105.5 metres.

author-image
SMEStreet Desk
New Update
BHEL, Atul Sobti, GAIL, Solar

Bharat Heavy Electricals Limited (BHEL) has successfully commissioned one more pumping unit (Unit 5) of 116 MW of the 7x116 MW Kaleshwaram Lift Irrigation Scheme (LIS) Package-6 in Telangana. BHEL has earlier commissioned 4 Units of the same project in April and May, 2019. Significantly, the pump for each unit is designed to lift 89.16 cumecs (cubic metres per second) of water by 105.5 metres.

Being developed by the Irrigation & CAD (I&CAD) department of the Government of Telangana, the greenfield lift irrigation project (formerly known as Pranhita Chevella) is located in Peddapalli district of Telangana. In the project, water shall be lifted from Sripada Yellampalli reservoir to Medaram reservoir and will be used for irrigation and water supply in nearby areas.

BHEL